Michael's Cove
Project consisted of removing sediments from Michael’s Cove connected to Lake Austin along Westlake Drive. Original depth of cove varied from 6 to 24 inches and was dredged to 3 to 6 feet in depth. Over an 8 week schedule, approximately 360 truck loads of material was hauled offsite. Aquatic plants were planted to rehabilitate the wetlands after construction.